Offshore Substation Installation Methodology
For details of the code implementation, please see Offshore Substation Installation API.
Overview
The OffshoreSubstationInstallation
module simulates the installation of
offshore substations and their associated substructures. ORBIT currently only
considers monopile substructures, though future release will extend this module
to include an option for jacket substructures. The installation of the
substructure and substation topside is completed with an installation vessel
while components are delivered to site using a feeder barge.
Processes
Port Operations
The feeder barge loads and fastens components on deck at port using the port crane. The default times for fastening each component to deck are listed below.
Component |
Inputs |
Default |
---|---|---|
Monopile |
|
12h |
Topside |
|
2h |
Currently, all vessels are only able to load multiples of complete sets of components (monopile and topside).
Monopile Installation
Monopile substructures are installed using the installation processes outlined
in the MonopileInstallation
module (process
diagram with feeder barges).
Topside Installation
Once the monopile is installed on-site, the topside can be released from deck storage and attached to the substructure. The following processes outline the code the processes the installation vessel takes to complete this task:
Action |
Inputs |
Default |
---|---|---|
Reequip Crane |
|
1h |
Release Topside |
|
2h |
Lift Topside |
wtiv.crane_rate wave_height |
calculated |
Pump Grout |
|
2h |
Cure Grout |
|
24h |
Jack-down |
depth, extension speed_above_depth speed_below_depth |
calculated |